Description:

The Center Street Erosion Control Improvements Projects is another great example of all of our companies working together. Lobar Design and Engineering, under the supervision of Chad Laughman, was in charge of the retaining wall design. Both the Lobar Associates and Site Development crews helped out as well. The project consisted of stream channel and embankment stabilization for erosion control including riprap apron, rock stabilization, erosion control matting, live stake plantings, cast in place concrete retaining wall, and cast in place concrete storm sewer headwall.